鶹Ƶ

Skip to content

BHP to make decision on Jansen project by February 2021

JANSEN — BHP is expecting its board of directors to make a final decision on its Jansen Potash project by February 2021. The date was announced in the company’s quarterly operational review released on Oct. 17.
BHP Jansen
Submitted photo by BHP

JANSEN — BHP is expecting its board of directors to make a final decision on its Jansen Potash project by February 2021.

The date was announced in the company’s quarterly operational review released on Oct. 17.

“In order to make a final investment decision, work on engineering to support project planning and on finalizing the port solution is required, and the Board has approved US$144 million for these activities,” said the report.

“An additional US$201 million in funding was approved to further derisk the project, focusing on the mine’s scope of work, advancing other engineering and procurement activities, and preparation works for underground infrastructure.”

The review also said that the company’s US$2.7 billion investment to finish the excavation and lining of the production and service shafts, as well as to continue the installation of essential surface infrastructure and utilities is 84 per cent complete, with the preparation work for the final shaft lining continuing.

push icon
Be the first to read breaking stories. Enable push notifications on your device. Disable anytime.
No thanks